| YEAR |
CLIENT |
PROJECT TITLE |
BRIEF DESCRIPTION OF WORKS |
| 1996 |
Bina Puri - Panzana Consortium JV.
(Design & Build) |
Upgrading of State Road B20 to form the Eastern Access to Kuala Lumpur International Airport.
- Package 1A
|
Rehabilitation and upgrading of 7km of road from two lane single carriageway to two-lane dual carriageway & reconditioning of 4 km of main access road inclusive of road alignment & drainage, multi-span bridges over road & rail, geotextile reinforced pile embankment, relocation of services and road furniture.
|
| 1997 |
Bina Puri - Panzana Consortium JV.
(Design & Build) |
Upgrading of State Road B20 to form the Eastern Access to Kuala Lumpur International Airport.
- Package 1B1
|
Rehabilitation and upgrading of 4 km of road from two lane single carriageway to two-lane dual carriage way - design road alignment, drainage, pre-consolidation with PVD & surcharge embankment.
|
| 1999 |
Bina Puri - Panzana Consortium JV.
(Design & Build) |
Upgrading of State Road B20 to form the Eastern Access to Kuala Lumpur International Airport.
- Package 1B2
|
Geometric design of 7km new alignment two-lane dual carriageway including one trumpet interchange, one directional ramp, elevated structures and surcharging of embankment.
|
| 2000 |
MOLOP Corporation Sdn. Bhd.
(Design & Build)
|
Upgrading of Federal Route 8 from Kuala Lipis to Kampung Relung, Pahang .
|
Geometric design of realignment and improvement of existing hilly terrain road to PWD R5 standard with deep cuts and high embankments.
|
| 2001 |
TAZAL Corporation Sdn Bhd.
(Design & Build) |
Hill road from Bertam Valley to Ringlet, Cameron Highlands, Pahang.
- Package 4
|
Geometric design to PWD R3 standard of new road and re-alignment of existing road totalling 19 km in mountainous terrain including 4 multi span bridges, extensive slope treatment and rigid pavements.
|
| 2002 |
Public Works Department Malaysia. |
Upgrading of Jalan Kedai Buloh - Kuala Besar from Simpang Empat Kedai Buloh to Jalan Pengkalan Chepa, Kelantan.
- Phase IV
|
Design of two lane single carriageway road from Simpang Empat Kedai Buloh to Pengkalan Chepa and two lanes dual carriageway from Pengkalan Chepa to Jalan Nangka including geometric design of road alignment, drainage and one multi span bridge.
|